software verification & validation plan is developed and followed by the
V&V team it details how the team wil verify and validate all activities
during the development cycle.  It should cover activities by all of the
different teams in development, docs, engineering, test, etc., and all
the the phases of the development cycle.  In the definition of test
plan below you could replace testing and test with V&V

Validation: The process of evaluating software to determine compliance
with specified requirements.

Verification: The process of evaluating the products of a given software
development activity to determine correctness and consistency with
respect to the products and standards provided as input to that activity.

Test Plan: A formal or informal plan to be followed to assure the
controlled testing of the product under test.

I don't have the information with me but IEEE has standards documents
for both Software Test Plans and Software V&V Plans.

G05070225 2004-6-29 17:05

我来总结一下

测试计划: 测试活动的组织与规划

确      认:保障做正确的产品的过程,有没有完成预定的产品规格,产品包需求。
验      证:保障产品做的正确的过程,在实现产品规格、产品包需求过程中有没有出现错误,产品在完成一定功能过程中,是不是会出现错误。

abba2004 2004-6-30 16:03

测试计划/测试确认/测试验证的主要区别就是他们存在于整个项目或者产品开发进程中的不同阶段

测试计划:起步阶段
测试确认:开发阶段,配合需求(单元测试)
测试验证:QA阶段(系统测试,集成测试)

东方一华 2004-7-21 16:15

testing

time 2004-10-1 20:04

有收获

msfox 2004-11-4 16:14

写错了吧,应该是测试,确认和验证的区别吧,测试计划和其他两项不是同一个范畴a

zxyjudy 2004-11-9 10:17

有收获

yangbohustwb 2007-9-17 19:21

谢谢

wxj234 2007-9-18 15:31

最好是有实例